Progress

    Time table of the project 

2005-2009 2009-2011 Q4 2011
Project development
  • 23 April 2009 contract signing main contractor
Start (commercial) operations and ready to supply to partners
  • Design and construction 

 Enecogen

    Progress summary construction

    • Notice to Proceed: 23 April 2009
    • Piling completed
    • Main Foundations Complete
    • Turbine hall steelwork progressing with main structure & crane rails complete and external cladding installation commenced.
    • Administration building structure completed internal finishes ongoing.
    • HRSG frame erection complete, casing panel installation commenced.
    • Construction Cooling water Intake/outfall progressing.
    • 380kV Cable Interconnection progressing 7/12km installed.
    • Gas pipeline interconnection construction commenced at Krabbeweg and pipe laid out at Markweg

    Images - HRSE erection

    Images - Diffuser unit 1 & AUx boiler

    Images - Overhead cranes unit 1 installed

    Images - Demin and raw water tanks

    Images - Cooling water infrastructure

    Images - Gas pipe delivery on Markweg

    Images - Cable Trench Construction

    Image - Site overview March 2010

    Key dates construction program

      • Turboset Foundations ready - Q1 2010
      • Main Equipment on site  - Q3 2010
      • HV Grid connection  - Q1 2011
      • Fuelgas connection  - Q1 2011
      • HRSG’s ready - Q2 2011
      • Hot commissioning  - Q3 2011
      • Start commercial operation - Q4 2011