Search
Contact
088 - 895 1801
info@enecogen.nl
Postal address:
Postbox 96
2900 AB Capelle a/d IJssel
The Netherlands
Visiting address:
Rivium Quadrant 75
2909 LC Capelle a/d IJssel
The Netherlands
Home
News
Project
Progress
Location
Partners
Parties
Main contractors
Authorities
Environment & Technology
Vacancies
SHE/QA Officer
Werkvoorbereider Maintenance
Operators
Shiftteamleaders
Teamleaders
Technicians
Plant Performance Engineer
Progress
Location
Enecogen
Project
Progress
Progress
Time table of the project
2005-2009
2009-2011
Q4 2011
Project development
23 April 2009 contract signing main contractor
Start (commercial) operations and ready to supply to partners
Design and construction
Progress summary construction
Notice to Proceed: 23 April 2009
Piling completed
Main Foundations Complete
Turbine hall steelwork progressing with main structure & crane rails complete and external cladding installation commenced.
Administration building structure completed internal finishes ongoing.
HRSG frame erection complete, casing panel installation commenced.
Construction Cooling water Intake/outfall progressing.
380kV Cable Interconnection progressing 7/12km installed.
Gas pipeline interconnection construction commenced at Krabbeweg and pipe laid out at Markweg
Key dates construction program
Turboset Foundations ready - Q1 2010
Main Equipment on site - Q3 2010
HV Grid connection - Q1 2011
Fuelgas connection - Q1 2011
HRSG’s ready - Q2 2011
Hot commissioning - Q3 2011
Start commercial operation - Q4 2011
Choose text size
Privacy Statement
|
Disclaimer
|
Sitemap